Interaction with the PRA before and during a model change application

2.1

This chapter sets out the PRA’s expectations on firms when interacting with the PRA before and during a model change application, as well as interaction with the PRA when altering an internal model change policy.

Interaction with the PRA before a model change application

2.2

The PRA expects firms to engage as early as possible with their supervision teams about planned changes and developments to their internal models. This should include any model changes that may arise from expected future changes in the firm’s risk profile: for example as a result of a potential business transaction. In particular, the PRA expects firms to give notice of their proposed model change application(s) as soon as firms consider an application likely.

2.3

When giving notice of a model change application, the PRA expects firms to provide a summary of their planned model change(s), the reasons for the change(s), the potential impact (both qualitative and quantitative) and the intended timescales for implementation.

2.4

The PRA expects firms to discuss the scope of their model change application with their usual supervisory contact. The PRA expects model change applications to address past PRA feedback, past data audits, limitations of the model, improvements driven by ongoing use of the model[2], validation findings and findings arising from the PRA’s supervisory review process. In addition, the PRA expects firms to articulate clearly how they have identified and prioritised the model change(s) included in their application as opposed to other model improvements in their model development plan.

Footnotes

2.5

The PRA will discuss with firms whether it would be useful to enter into a pre-application review process before submitting a formal model change application. This is likely to depend on the complexity, scale and quantum of model changes proposed. The length of any pre-application will also be subject to discussion with the PRA and will reflect the extent of review work considered necessary. If firms choose to make use of a pre-application period, feedback would be provided by the PRA during this process; however, this is not a substitute for the firm’s own internal governance or validation process.

2.6

The PRA expects firms to submit no more than one model change application per year. This application may comprise several individual major changes (and include any extensions of scope of the internal model), which will be reviewed together under the same supervisory approval process. This will help to ensure that firms are able to provide robust governance over model changes and that the PRA is able to commit appropriate resources to the review of the application. However, the PRA understands that business or market conditions may, in some circumstances, lead to more than one model change application in a year.

2.7

A planned transaction (for example an acquisition or investment in a new asset class), or other event, may lead to a change in the firm’s risk profile, and the firm may therefore instigate a model change application. In such situations firms should consider whether the PRA can realistically approve the model change application by the time the transaction takes place. If approval of the model change application is not expected to be obtained in time, firms should discuss with the PRA how they will calculate revised capital requirements and remain adequately capitalised immediately after the transaction or event takes place.

2.8

Where an event occurs which causes a firm to consider whether changes might be required to its internal model, the PRA recognises that it might take some time for the firm to determine what changes are required and for any changes to be implemented within the model in a way that meets the Solvency II requirements. In such circumstances, the PRA expects firms to discuss with the PRA what other steps might be taken in the interim until a model change application can be made and a decision can be taken.

Interaction with the PRA during a model change application

2.9

Following the submission of a model change application, a firm should continue to use its existing approved internal model when determining its SCR for formal Solvency II reporting purposes. The firm should use the version of the model which has been approved on or before the last day of the reporting period for the purposes of Solvency II reporting at that date. However, the firm can include minor changes implemented within the existing approved internal model as long as these fall below the firm’s threshold in respect of accumulating minor changes.

2.10

The PRA expects firms to have regard to the possibility that a model change application is not approved. This should include having contingency plans, where appropriate, and sharing these with the PRA.

2.11

While the PRA does not formally approve minor model changes, it will regularly review firms’ reporting of minor changes[3] and may challenge any that it considers should be classified as a major model change. In addition, minor changes may be subject to review by the PRA at any time as part of the PRA’s ongoing supervisory review process. If a minor change causes the model to no longer meet the Solvency II tests and standards, firms must address this issue.4 Minor change accumulations will be reset at the end of an annual cycle (that firms may specify), or at the point of receiving a major change application (if that application is approved), unless otherwise agreed with the PRA.

Footnotes

  • 3. As per Guideline 8 of EIOPA’s Guidelines on the use of internal models.
  • 4. Solvency Capital Requirement – Internal Models, rule 9.1.

2.11A

Firms are encouraged to discuss accumulated minor changes with the PRA prior to resetting accumulations to zero in order to ensure a common understanding of the interaction between the various minor changes and the model as a whole.

2.12

Firms are reminded that they should remain adequately capitalised at all times,[5] including the period when a model change application is being reviewed by the PRA. The PRA may consider use of supervisory tools (including as a temporary measure) to ensure that any risks are adequately mitigated.

Footnotes

  • 5. Rule 2.4 in the Fundamental Rules Part of the PRA Rulebook and rule 2.1 of the Solvency Capital Requirement – General Provisions Part.

2.13

In demonstrating ongoing compliance with the use test, firms are reminded to consider Guideline 12 (Use test and changes to the internal model) of the European Insurance and Occupational Pensions Authority (EIOPA) guidelines on the use of internal models.

Alterations to the policy for changing the internal model

2.14

The PRA expects a firm to discuss with its normal supervisory contact a plan to alter its internal model change policy. Such plans may be made in a separate application and will be reviewed on a standalone basis by the PRA. Alternatively, a firm may wish to align an application to alter its internal model change policy with an existing model change application.